Monday, 16 January 2012

CONSTRUCTION SCHEDULE


We have a rough schedule/time line for the construction of our building!  Please keep in mind that there are many factors (such as weather) that can have an effect on the accuracy  of the timeline, however this will give you a good idea of how things will progress.

So far we have completed:
Excavation
Site Services
Trench Footings
Water Proofing
Basement Forming
1st Floor Structural Steel
Backfill Foundations
Slab/Bsmt Mechanical
Backfill/Prep Slabs


Currently in production:
Structural Steel
Plumbing

Next Up:
Precast Concrete


Still to come:
Precast Concrete Installation – 1/24/12
Rough Carpentry Roof – 1/24/12
Roofing – 2/3/12
Aluminum Glazing (frames) – 2/28/12
Elec. Mech. R/I ext walls – 2/28/12
Heat – 3/14
Plumbing RI U/G – 3/28/12
Pour Floor – 4/12/12
Exterior Masonry – 4/16/12
Steel Stud Framing (Interior) – 4/24/12
Exterior Finish Grading – 5/1/12
Electrical – 5/3/12
Plumbing/Roof Drains – 5/3/12
Ceilings – 5/8/12
Exterior Sidewalk Paving – 5/9/12
HVAC Rough In – 5/15/12
Sprinklers – 5/15/12
Drywall – 5/29/12
Painting – 6/13/12
Doors & Hardware – 6/26/12
Install Fixtures – 7/4/12
Clean Up – 7/10/12
PROJECT FINISH – 7/17/12


Please remember these are only estimate times!  We will keep you updated every step of the way.  Remember to keep praying for favor and God’s provision in this project.

No comments:

Post a Comment