We have a rough schedule/time line for the construction of
our building! Please keep in mind that
there are many factors (such as weather) that can have an effect on the
accuracy of the timeline, however this
will give you a good idea of how things will progress.
So far we have completed:
Excavation
Site Services
Trench Footings
Water Proofing
Basement Forming
1st Floor Structural Steel
Backfill Foundations
Slab/Bsmt Mechanical
Backfill/Prep Slabs
Currently in production:
Structural Steel
Plumbing
Next Up:
Precast Concrete
Still to come:
Precast Concrete Installation – 1/24/12
Rough Carpentry Roof – 1/24/12
Roofing – 2/3/12
Aluminum Glazing (frames) – 2/28/12
Elec. Mech. R/I ext walls – 2/28/12
Heat – 3/14
Plumbing RI U/G – 3/28/12
Pour Floor – 4/12/12
Exterior Masonry – 4/16/12
Steel Stud Framing (Interior) – 4/24/12
Exterior Finish Grading – 5/1/12
Electrical – 5/3/12
Plumbing/Roof Drains – 5/3/12
Ceilings – 5/8/12
Exterior Sidewalk Paving – 5/9/12
HVAC Rough In – 5/15/12
Sprinklers – 5/15/12
Drywall – 5/29/12
Painting – 6/13/12
Doors & Hardware – 6/26/12
Install Fixtures – 7/4/12
Clean Up – 7/10/12
PROJECT FINISH – 7/17/12
Please remember these are only estimate times! We will keep you updated every step of the
way. Remember to keep praying for favor
and God’s provision in this project.