Monday, 16 January 2012

CONSTRUCTION SCHEDULE


We have a rough schedule/time line for the construction of our building!  Please keep in mind that there are many factors (such as weather) that can have an effect on the accuracy  of the timeline, however this will give you a good idea of how things will progress.

So far we have completed:
Excavation
Site Services
Trench Footings
Water Proofing
Basement Forming
1st Floor Structural Steel
Backfill Foundations
Slab/Bsmt Mechanical
Backfill/Prep Slabs


Currently in production:
Structural Steel
Plumbing

Next Up:
Precast Concrete


Still to come:
Precast Concrete Installation – 1/24/12
Rough Carpentry Roof – 1/24/12
Roofing – 2/3/12
Aluminum Glazing (frames) – 2/28/12
Elec. Mech. R/I ext walls – 2/28/12
Heat – 3/14
Plumbing RI U/G – 3/28/12
Pour Floor – 4/12/12
Exterior Masonry – 4/16/12
Steel Stud Framing (Interior) – 4/24/12
Exterior Finish Grading – 5/1/12
Electrical – 5/3/12
Plumbing/Roof Drains – 5/3/12
Ceilings – 5/8/12
Exterior Sidewalk Paving – 5/9/12
HVAC Rough In – 5/15/12
Sprinklers – 5/15/12
Drywall – 5/29/12
Painting – 6/13/12
Doors & Hardware – 6/26/12
Install Fixtures – 7/4/12
Clean Up – 7/10/12
PROJECT FINISH – 7/17/12


Please remember these are only estimate times!  We will keep you updated every step of the way.  Remember to keep praying for favor and God’s provision in this project.

Tuesday, 10 January 2012

THE WORD IS OUR FOUNDATION!


 On Thursday, January 5 and Sunday, January 8, 2012.  The members of Toronto City Church had an opportunity to permanently etch the scriptures that God placed on their heart for TCC on to the steel beams of our new building!



Tuesday, 3 January 2012

Update - January 3, 2012!

Well.....construction is well underway at 36 Curity Avenue!  The remainder of the previous structure is out, the foundations of Phase II in, and the steel has arrived on site.  Here are some pictures taken today.





Hopefully within the next couple of posts we will have a full schedule for you.

Wednesday, 28 September 2011

Signed. Sealed. Delivered!

Great News! The financing has been approved and the papers have been signed!!

It's time to build Toronto City Church!

It should only be a matter of days before construction will re-commence and we are very excited. The project should take 8 months to complete which means that by Summer 2012 we will be celebrating in a brand new facility that is ours.

So what now? We need to keep giving, keep praying and believe God like never before that we will have a great impact on this city!

Thursday, 19 May 2011

Almost There!


Although I would love to say that we met our goal by May 8, I have to report that we are just shy of it.  Now…it would be easy to get discouraged, however it is in times like these that we need to be even MORE confident in God’s faithfulness!  As I sit here and write this I am reminded of the wonderful words of encouragement and faith that came forth a few weeks ago as God spoke to the hearts of many people in the Arise series we just had with Pastor Len Zoeteman.  

Here are some of those scriptures:

Scriptures That  Exalt God

Isaiah 55:8-11  (Shantha J.)

Psalm 30:24 (Adrian S.)

Mark 4:30-32 (Denny M.)

Joshua 2:9-11 (Lisa L.)

Psalm 37:3 (Mark G.)

Hebrews 12:1-2 (Allan M.)

Scriptures of the Blessing, Goodness & Increase of God

Psalm 102:13-22 (Karan A.)

2 Corinthians 9:10-15 (Anna S.)

Isaiah 54:2-5 (Len Z.)

Isaiah 60:1-7 (Michelle M.)

Isaiah 55:8-13 (Les B.)

Mark 10:27-31 (Katherine Y.)

1 John 5:4 (Len Z.)